Download Solution PDFA, B and C can complete a work in 12, 15 and 20 days, respectively. How many days are required to finish the work if they work together?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
Time taken by A to complete the work = 12 days
Time taken by B to complete the work = 15 days
Time taken by C to complete the work = 20 days
Formula used:
Time required to complete the work when A, B, and C work together = 1 / (Total work done by A, B, and C together in 1 day)
Calculation:
Work done by A in 1 day = 1 / 12
Work done by B in 1 day = 1 / 15
Work done by C in 1 day = 1 / 20
Total work done by A, B, and C together in 1 day = 1 / 12 + 1 / 15 + 1 / 20
Finding a common denominator:
LCM of 12, 15, and 20 = 60
Work done by A, B, and C together in 1 day = (5 + 4 + 3) / 60 = 12 / 60 = 1 / 5
Time required to complete the work = 1 / (1 / 5) = 5 days
∴ The work will be completed in 5 days if A, B, and C work together.
Last updated on May 28, 2025
-> The SSC has released the SSC CHSL exam calendar for various exams including CHSL 2025 Recruitment. As per the calendar, SSC CHSL Application process will be active from 23rd June 2025 to 18th July 2025.
-> The Exam Date for the SSC CHSL 2025 will be from 8th September 2025 to 18th September, 2025.
-> The SSC CHSL is conducted to recruit candidates for various posts such as Postal Assistant, Lower Divisional Clerks, Court Clerk, Sorting Assistants, Data Entry Operators, etc. under the Central Government.
-> The SSC CHSL Selection Process consists of a Computer Based Exam (Tier I & Tier II).
-> To enhance your preparation for the exam, practice important questions from SSC CHSL Previous Year Papers. Also, attempt SSC CHSL Mock Test.