What is the correct sequence of activities in SDLC?

This question was previously asked in
Beltron Programmer 1 Oct 2023 Official Paper
View all BELTRON Programmer Papers >
  1. planning, development, testing, designing, deployment and maintenance
  2. planning, development, testing, deployment, designing and maintenance
  3. planning, designing, testing, deployment, development and maintenance
  4. planning, designing, development, testing, deployment and maintenance

Answer (Detailed Solution Below)

Option 4 : planning, designing, development, testing, deployment and maintenance
Free
Beltron Programmer Mock Test
0.8 K Users
20 Questions 20 Marks 24 Mins

Detailed Solution

Download Solution PDF

The correct answer is Option 4) planning, designing, development, testing, deployment and maintenance.

Key Points

  • Software Development Life Cycle (SDLC) is a structured process followed to develop software efficiently and effectively.
  • The standard sequence of phases in SDLC is as follows:
    1. Planning: Understanding the project scope, feasibility, and resource estimation.
    2. Designing: Creating the architecture and design specifications.
    3. Development: Writing and building the code according to the design.
    4. Testing: Verifying that the software works correctly and is free of bugs.
    5. Deployment: Delivering the software to end users or moving it to production.
    6. Maintenance: Performing updates, bug fixes, and enhancements after deployment.

Additional Information

  • Option 1: Incorrect order — development comes before design, which is not practical or logical.
  • Option 2: Testing comes before designing — also incorrect sequence.
  • Option 3: Development appears after deployment — again incorrect.
  • Option 4: ✔️ Correct — follows the widely accepted SDLC model (like Waterfall or Agile with phases).

Conclusion: The correct SDLC sequence is: planning → designing → development → testing → deployment → maintenance.

Latest BELTRON Programmer Updates

Last updated on Nov 25, 2024

-> BELTRON Programmer 2024 Notification has been released on the official website.

-> The Bihar State Electronics Development Corporation Limited (BELTRON) has announced a recruitment drive for Programmer positions on a contractual basis.

-> Specific vacancy details will be shared separately.

-> Interested candidates can apply online from November 11, 2024, to December 10, 2024.

-> The Minimum age of the candidates should be 21 years and maximum age should be 59 year of age. 

Get Free Access Now
Hot Links: teen patti apk teen patti apk download online teen patti all teen patti game