As per the Software Engineering Institute (SEI), the correct sequence is

A. Initial

B. Repeatable

C. Managed

D. Optimizing

E. Defined

Choose the correct answer from the options given below:

  1. A, B, C, D, E
  2. A, B, E, C, D
  3. A, E, C, D, B
  4. A, E, B, C, D

Answer (Detailed Solution Below)

Option 2 : A, B, E, C, D

Detailed Solution

Download Solution PDF

The correct answer is : option 2

Key Points

As per the Software Engineering Institute (SEI), the correct sequence for the Capability Maturity Model Integration (CMMI) levels is:

  1. Initial
  2. Repeatable
  3. Defined
  4. Managed
  5. Optimizing

This sequence reflects the stages of maturity that organizations go through as they improve their software engineering processes. Therefore, the correct answer, which aligns with option 2, is:

Option 2: A, B, E, C, D