The whole area behind the dam draining into a stream or river across which the dam is constructed is known as: 

This question was previously asked in
SJVN ET Mechanical 2019 Official Paper
View all SJVN Executive Trainee Papers >
  1. Surge tank
  2. Catchment area
  3. Spillways
  4. Reservoir

Answer (Detailed Solution Below)

Option 2 : Catchment area
Free
SJVN ET General Awareness Mock Test
0.8 K Users
20 Questions 20 Marks 12 Mins

Detailed Solution

Download Solution PDF

Explanation:

Catchment Area

  • The catchment area refers to the entire geographical region that drains into a specific stream, river, or other water body. In the context of a dam, it is the area from which all precipitation (rainfall, snowmelt, etc.) flows into the reservoir behind the dam. The boundaries of a catchment area are determined by natural topographical features, such as ridges and hills, which separate one drainage basin from another.

When a dam is constructed across a river or stream, the catchment area becomes a critical factor in determining the water inflow into the reservoir. This inflow is essential for various purposes, including hydroelectric power generation, irrigation, water supply, flood control, and more. The total volume of water that can be collected in the reservoir is directly proportional to the size and characteristics of the catchment area. Key aspects of the catchment area include:

  • Size of the Catchment Area: Larger catchment areas generally contribute more water to the reservoir because they collect precipitation over a broader region. However, the efficiency of water collection also depends on other factors like soil permeability and vegetation cover.
  • Topography: The shape and slope of the terrain influence the flow of water. Steeper slopes facilitate quicker runoff, while flatter areas may allow more water to infiltrate into the ground.
  • Climate: The amount and pattern of rainfall in the catchment area determine the volume of water that can be collected. Seasonal variations, such as monsoons, play a significant role in regions with distinct wet and dry periods.
  • Land Use: Human activities, such as agriculture, deforestation, and urbanization, can impact the runoff characteristics of the catchment area. For instance, deforestation may lead to increased surface runoff and reduced groundwater recharge.
  • Hydrology: The natural drainage network, including rivers, streams, and tributaries, influences how efficiently water is channeled into the reservoir.

Importance of the Catchment Area in Dam Construction:

Understanding the catchment area is vital for the planning and operation of a dam. Key reasons include:

  1. Reservoir Capacity Estimation: The size and characteristics of the catchment area help engineers calculate the maximum potential water inflow, which is crucial for determining the reservoir's storage capacity.
  2. Flood Management: A well-designed dam takes into account the peak runoff from the catchment area during heavy rainfall to prevent overflow and downstream flooding.
  3. Water Resource Planning: Accurate knowledge of the catchment area allows for efficient allocation of water for various purposes, such as irrigation, drinking water supply, and industrial use.
  4. Environmental Impact Assessment: The catchment area influences the ecological balance of the region, affecting flora, fauna, and local communities. Proper assessment ensures sustainable development.
Latest SJVN Executive Trainee Updates

Last updated on Jul 15, 2025

-> SJVN Executive Trainee Written Exam date is out, The computer based exam will be held on 10th, 14th August 2025.

->SJVN Executive Trainee recruitment 2025 application form has been released. Applicants can apply for the SJVN recruitment 2025 Executive Trainee till May 18.

->SJVN Limited has announced the recruitment notification for the position of Executive Trainee 2025.

->A total of 114 vacancies are available for the SJVN Executive Trainee Recruitment across various disciplines such as Civil, Mechanical, Electrical, Environment, Electronics & Communication, and more.

->The selection process of SJVN Executive Trainee recruitment 2025, as per the previous notification, includes a Computer-Based Test, Group Discussion, and Personal Interview.

->Once selected, candidates will be required to sign a service agreement bond of Rs. 10,00,000/- (Rs. 7,50,000/- for SC/ST/PWD candidates), committing to complete the prescribed training and serve the company for a minimum of 3 years.

->Candidates must refer to the SJVN Executive Trainee Previous Year Papers and boost their preparation for the exam.

Get Free Access Now
Hot Links: teen patti master real cash teen patti - 3patti cards game downloadable content teen patti lotus teen patti casino apk teen patti flush