Ten men begin to work together on a job, but after some days, 4 of them leave. As a result, the job which could have been completed in 40 days is completed in 50 days. How many days after the commencement of the work did the 4 men leave?

This question was previously asked in
Patna High Court Mazdoor Official Paper (Held On: 22 Jun, 2025)
View all Patna High Court Mazdoor Papers >
  1. 20 days
  2. 25 days
  3. 15 days
  4. 18 days

Answer (Detailed Solution Below)

Option 2 : 25 days
Free
Patna High Court Mazdoor: ST 1 General Knowledge & Awareness
2.1 K Users
20 Questions 20 Marks 48 Mins

Detailed Solution

Download Solution PDF

Given:

10 men can complete the job in 40 days.

Job actually completed in 50 days.

4 men left after working for some days.

Formula used:

Work done by men = Number of men × Number of days

Total work = Work done before leaving + Work done after leaving

Calculations:

Total work = 10 × 40 = 400 units

Work done before 4 men left = 10 × x = 10x

Work done after 4 men left = 6 × (50 - x) = 300 - 6x

⇒ Total work = Work done before leaving + Work done after leaving

⇒ 400 = 10x + (300 - 6x)

⇒ 400 = 10x + 300 - 6x

⇒ 400 - 300 = 4x

⇒ 100 = 4x

⇒ x = 100 / 4

⇒ x = 25

∴ The 4 men left after 25 days, hence the correct answer is option (2).

Latest Patna High Court Mazdoor Updates

Last updated on Jun 17, 2025

-> The Patna High Court Mazdoor 2025 Call Letter has been released on 16th June 2025.

-> A total of 171 vacancies have been released.

-> 8th/10th/12th-pass candidates are eligible for this post.

-> Applications for this recruitment were submitted online by 18th March 2025.

-> The selection process includes a Written Test, Cycling Test, Skill Test, and Interview.

-> The finally appointed candidates will be entitled to salary in the pay scale of INR 14800 to INR 40300 (Level -1).

More Time and Work Questions

Get Free Access Now
Hot Links: teen patti online teen patti yes teen patti master download teen patti master