Consider the following phases of project management:

1. Identification

2. Formulation

3. Appraisal

4. Implementation 

Which of the above phases are relevant, sequentially?

This question was previously asked in
UPSC ESE 2017 Paper 1
View all UPSC IES Papers >
  1. 1, 2 and 3 only
  2. 1, 2 and 4 only
  3. 3 and 4 only
  4. 1, 2, 3 and 4

Answer (Detailed Solution Below)

Option 4 : 1, 2, 3 and 4
Free
ST 1: UPSC ESE (IES) Civil - Building Materials
6.5 K Users
20 Questions 40 Marks 24 Mins

Detailed Solution

Download Solution PDF

Explanation:

There are 7 stage to project management but there are five stage mainly.

(a) Project identification

(b) Project preparation (project formulation)

(c) Project appraised

(d) Negotiation

(e) Project approval

(f) Project planning

(g) Project implementation

Latest UPSC IES Updates

Last updated on Jul 2, 2025

-> ESE Mains 2025 exam date has been released. As per the schedule, UPSC IES Mains exam 2025 will be conducted on August 10. 

-> UPSC ESE result 2025 has been released. Candidates can download the ESE prelims result PDF from here.

->  UPSC ESE admit card 2025 for the prelims exam has been released. 

-> The UPSC IES Prelims 2025 will be held on 8th June 2025.

-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.

-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.

More Project Management Questions

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti master old version all teen patti master teen patti comfun card online master teen patti