Question
Download Solution PDFWith reference to the following network which statement is incorrect?


Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
According to the above network following inferences can be drawn:
-
Event 1 is the starting event and Event 8 is the end event.
-
Event 2 precedes Event 3 and Event 4 and follows Event 2.
-
Event 3 precedes Event 5, Event 6, and Event 7 and follows Event 2.
-
Event 4 precedes Event 7 and follows Event 2.
-
Event 5 follows event 3 and precedes Event 6.
-
Event 6 precedes Event 8 and follows Event 5, Event 3, and Event 7.
-
Event 7 precedes Event 6 and follows Event 4 and Event 3.
Additional Information PERT (Program Evaluation and Review Technique)
-
Focus on Uncertainty
PERT is used for projects where activity durations are uncertain. It uses three estimates: optimistic (O), most likely (M), and pessimistic (P), to calculate the expected duration of each activity. -
Probabilistic Approach
PERT is a probabilistic tool that helps in determining the probability of completing the project within a certain time frame. It is suited for research and development projects or new product launches. -
Event Oriented
PERT networks are event-oriented, focusing on milestones (events) in the project timeline rather than on individual activities. -
Emphasis on Time
The primary goal of PERT is to estimate project duration and manage time-related uncertainties rather than costs. -
Complex Projects with High Risk
PERT is typically used for large, complex, and non-repetitive projects where uncertainty and risk are high.
CPM (Critical Path Method)
-
Focus on Activity Duration
CPM is used for projects with well-known and predictable activity durations. It focuses on determining the critical path, which is the longest sequence of activities in a project. -
Deterministic Approach
CPM uses a deterministic model where activity times are assumed to be known and fixed, making it ideal for construction or manufacturing projects. -
Activity Oriented
CPM networks are activity-oriented. The focus is on the sequence and duration of tasks required to complete the project. -
Emphasis on Time and Cost
In addition to managing project duration, CPM also considers project costs. It helps in optimizing both time and cost through techniques like crashing. -
Suitable for Repetitive Projects
CPM is often used in industries like construction, engineering, and production, where projects are repetitive and experience-based.
Last updated on Jul 1, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been rescheduled on its official website.
-> JKSSB JE exam will be conducted on 31st August (Civil), and on 24th August 2025 (Electrical).
-> JKSSB JE application form correction facility has been started. Candidates can make corrections in the JKSSB recruitment 2025 form from June 23 to 27.
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from 18th May 2025 to 16th June 2025
-> Candidates who are preparing for the exam can access the JKSSB JE syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.