Question
Download Solution PDF_______ float is defined as the time through which an activity can be delayed without affecting the succeeding and preceding activities.
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation
Slack or Event Float
- Slack corresponds to the event in PERT.
- Float corresponds to activity in CPM.
Slack
- It is defined as the amount of time by which an event can be delayed without delaying the project schedule.
- Slack of an event = Latest Start Time – Earliest Start Time OR Latest Finish Time – Earliest Finish Time
There are three types of floats.
Total Float (TF) |
|
Free Float (FF) |
· Part of the Total Float, which can be used without affecting the float of succeeding activity. · Extra time by which an activity can be delayed so that the succeeding activity can be started on earliest start time.
|
Independent Float (IF) |
|
Last updated on Jul 1, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been rescheduled on its official website.
-> JKSSB JE exam will be conducted on 31st August (Civil), and on 24th August 2025 (Electrical).
-> JKSSB JE application form correction facility has been started. Candidates can make corrections in the JKSSB recruitment 2025 form from June 23 to 27.
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from 18th May 2025 to 16th June 2025
-> Candidates who are preparing for the exam can access the JKSSB JE syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.