The various treatment processes in a water treatment plant are as follows :

1. Filtration

2. Chlorination

3. Sedimentation

4. Coagulation

5. Flocculation

The correct sequence of these processes in water treatment is

This question was previously asked in
APSC JE Civil 14 Jul 2024 Official Paper
View all APSC JE Papers >
  1. 1, 2, 3, 4, 5
  2. 4, 5, 3, 1, 2
  3. 2, 3, 1, 5, 4
  4. 1, 2, 5, 3, 4

Answer (Detailed Solution Below)

Option 2 : 4, 5, 3, 1, 2
Free
APSC JE Civil Surveying Mock Test
20 Qs. 20 Marks 25 Mins

Detailed Solution

Download Solution PDF

Explanation:

Sequence of Water Treatment Processes

Water treatment involves a series of processes to remove impurities and make it safe for consumption. The correct sequence ensures optimal removal of contaminants and effective purification.

  • Coagulation: Chemicals are added to destabilize particles and cause them to clump together.

  • Flocculation: Gentle mixing encourages clumped particles to form larger aggregates called flocs.

  • Sedimentation: Flocs settle at the bottom of the tank, separating from the water.

  • Filtration: Remaining impurities are removed by passing water through filter beds.

  • Chlorination: Chlorine is added to kill pathogens and disinfect the water.

Analyzing the Given Options

  1. Option 1: 1, 2, 3, 4, 5

    • This sequence starts with filtration, which is incorrect since coagulation and flocculation must precede filtration.

    • Hence, this option is incorrect.

  2. Option 2: 4, 5, 3, 1, 2

    • This sequence correctly starts with coagulation and flocculation, followed by sedimentation, filtration, and chlorination.

    • Hence, this option is correct.

  3. Option 3: 2, 3, 1, 5, 4

    • This sequence starts with chlorination, which is incorrect as it should be the final step.

    • Hence, this option is incorrect.

  4. Option 4: 1, 2, 5, 3, 4

    • This sequence starts with filtration, which is incorrect since coagulation must precede filtration.

    • Hence, this option is incorrect.

Conclusion:

The correct sequence of water treatment processes is Option 2: 4, 5, 3, 1, 2.

Latest APSC JE Updates

Last updated on Jul 12, 2025

-> APSC JE recruitment 2025 notification released under the Soil Conservation Department. Candidates can apply for the recruitment from July 16 to August 15 (26/2025).

-> APSC JE Admit Card 2025 is released on 11th July 2025. Candidates who have applied for APSC JE can download their admit card from official website.

-> For the Adv 05/2025, the APSC JE Civil Exam date 2025 has been released. As per the new schedule, the exam will be conducted on July 20.

->APSC JE recruitment 2025 notification released for Mechanical Engineering.

->A total of 17 vacancies are announced for the Water Resource Department under Adv. No, 18/2025.

->APSC JE final result for Adv. No. 10/2024 has been released in PDF. 

->APSC JE Civil Engineer recruitment notification has been released for the Fishery Department. 

->Applicants can fill the APSC JE application form for Civil Engineer, Fishery Department from May 3. A total of 32 vacancies have been announced. 

->APSC JE 2025 document verification schedule released (10/2024).

-> The APSC JE Notification 2025 has been released for 650 vacancies of AE Civil under the Public Works Roads Department (PWRD) & Public Works (Building & NH) Department. 

-> The recruitment is also ongoing for 80 vacancies of Advt. No. 10/2024. For the same, the Screening Test (OMR Based) was held on 22nd December 2024.

-> Candidates with an Engineering Diploma are eligible for this post.

-> Prepare for the exam using APSC JE Test Series and APSC JE Previous Year Papers.

Hot Links: teen patti customer care number lucky teen patti teen patti refer earn teen patti 500 bonus