Question
Download Solution PDF30 men working 7 hrs a day can do a work in 18 days. In how many days will 21 men working 9 hrs a day do the same work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
Number of men (M1) = 30
Hours per day (H1) = 7
Number of days (D1) = 18
For the second case:
Number of men (M2) = 21
Hours per day (H2) = 9
Number of days (D2) = ?
Formula used:
Since the total work remains constant:
M1 × H1 × D1 = M2 × H2 × D2
Calculation:
30 × 7 × 18 = 21 × 9 × D2
⇒ D2 = (30 × 7 × 18) / (21 × 9)
⇒ D2 = 20 days
∴ The correct answer is option (1).
Last updated on May 26, 2025
-> The Chandigarh Police Constable Recruitment 2025 will be released soon.
-> A total of 400 vacancies will be released soon.
-> Candidates with a Bachelors/Masters degree in the concerned stream are eligible for this post.
-> The selection process includes a written test, Physical Efficiency Test/ Physical Measurement Test (PET/PMT), and Document Verification.
-> Prepare for the exam with Chandigarh Police Constable Previous Year Papers.